If a contractor didn't finish the work in Saudi Arabia, you can take legal action, and the first step is almost always a formal notice to the contractor. Once the contractor has been notified and still does not perform, the Civil Transactions Law lets you ask the court to order completion, to terminate the contract and recover what you paid beyond the value of the work done, or to have another contractor finish at the first contractor's expense, with compensation for proven loss in each case.
Key takeaways
- Send a formal written notice first: under Article 175, compensation is normally due only after notice.
- You can ask for completion, termination with restitution, or completion by another contractor at the first one's cost.
- Bringing in a new contractor needs court permission under Article 167, except in urgent cases.
- Record the site with photos and an engineer's report before anyone else touches it.
- Claims are filed on Najiz; you need the contractor's ID number, and an iqama is accepted as your ID.
The law that applies: the Civil Transactions Law, issued by Royal Decree M/191 dated 29/11/1444H, now sets the general rules on breach of contract, formal notice and compensation in Saudi Arabia. The articles cited here were checked against the text published in Umm Al-Qura in October 2026.
Can I sue a contractor who stopped work?
Yes. Article 107 of the Civil Transactions Law says that in a contract binding on both sides, if one party fails to perform, the other party may, after giving formal notice, ask for the contract to be performed or terminated, with compensation where it is due. A construction or renovation contract fits this exactly: you pay, and the contractor builds what was agreed.
There is one limit worth knowing before you file. The same article lets the court refuse termination if the part left unperformed is of minor importance compared with the whole obligation. If only snagging or small finishing items remain, a claim for completion or for the cost of finishing is usually a better fit than asking to end the whole contract.
Do I have to send a formal notice first?
In most cases, yes. Article 175 says compensation is not due until the debtor (here, the contractor) has been given formal notice, unless an agreement or a legal provision says otherwise. Article 177 says notice can be given by any method the parties agreed or by the method the law sets for notification, so read the notices clause in your contract before you send anything.
Article 176 lists cases where notice is not required. The ones that matter most for building work are:
- the contract says the contractor is in default as soon as the completion date passes;
- performance has become impossible or pointless because of the contractor's own act;
- the contractor has stated in writing that he will not perform, for example a message saying he has left the project.
Even when notice is not strictly required, a clear written notice rarely hurts. It fixes the date from which the delay is counted and shows the court you gave the contractor a last chance.
What can I ask the court for?
Choosing the right claim shapes the whole case. These are the main options the law gives an owner:
| What you ask for | When it fits | Legal basis |
|---|---|---|
| An order that the contractor completes the work | The contractor can still finish and you are willing to keep him | Article 164: after notice, a debtor can be compelled to perform in kind where that is possible |
| Permission to complete at the contractor's cost | You have lost confidence and want a new contractor, with the first one paying the difference | Article 167: the creditor may ask the court for permission to have the work done at the debtor's expense |
| Termination and restitution | The breach is serious and you want out, recovering what you paid beyond the value of the work done | Articles 107 and 111: termination after notice, then both parties go back to their position before the contract |
| Compensation for delay | The delay itself cost you money, such as rent for other housing or lost business | Articles 171 and 175: a debtor who delays compensates the resulting harm, after notice |
Some of these can be combined, such as termination with compensation, or completion at the contractor's cost plus compensation for the delay. Article 164 also lets the court limit you to compensation if forcing the contractor to perform in kind would be seriously burdensome for him, and Article 171 excuses delay caused by something outside the contractor's control, so expect those arguments in the defence.
Can I bring in another contractor before the judgment?
As a rule, only with the court's permission. Article 167 makes completing the work at the defaulting contractor's expense subject to court permission, with an exception for urgent cases, where you may act without waiting.
Urgent means harm that cannot wait: an open roof before the rains, an unsupported excavation next to a neighbour's wall, exposed wiring in an occupied home. If you rely on the urgency exception, record the site before anyone touches it: dated photos and video, an engineer's report on what was built and its condition, and a note of what remains. Without that record, the first contractor can argue that the work was nearly finished or that the new contractor's price is inflated.
How do I file the case on Najiz?
Claims are filed online through Najiz. According to the Ministry of Justice guide to the file statement of claim service, the steps are:
- Sign in to Najiz with your National Single Sign-On (Nafath) account.
- Open All Electronic Services, choose the Judiciary package, then "File statement of claim".
- Pick the case category and read its requirements.
- Enter the case details and the parties. You must know the defendant's ID number to file.
- Upload your documents and submit.
You need a valid national ID, iqama or other accepted ID and a national address. If someone files for you, they need a valid power of attorney that includes the power to plead. You generally do not have to visit the court unless you receive a text message asking you to attend. Which court hears the case depends on who the parties are and what kind of contract it is, so it is worth getting the case category right before you submit.
If your project has stalled and you are not sure which claim fits, you can reach Alabdli Law Firm on +966 54 668 5254 or on WhatsApp before you send a notice or hire a replacement contractor.
What evidence do I need?
| Evidence | What it proves | Tip |
|---|---|---|
| Contract, drawings, bill of quantities | What was agreed, the price and the completion date | Check for clauses on notices, delay penalties and variations |
| Bank transfers and receipts | What you paid and when | Link each payment to a stage of the work |
| WhatsApp and email messages | Delays, excuses, admissions, a statement that he will not return | Export full chats with dates, not screenshots of single lines |
| Engineer's report, photos and video | What was built, its quality, and the cost to finish | Get it before any new contractor starts |
| The formal notice | That the contractor was told to perform | Keep proof of delivery |
Worked example with hypothetical figures
A homeowner in Jeddah signs a contract for a villa extension at 400,000 riyals and pays 250,000 riyals in stages. The contractor walks off the site. An independent engineer values the work done at 150,000 riyals and quotes 300,000 riyals for another contractor to finish.
- Termination and restitution: the core of the claim is what was paid beyond the value of the work done: 250,000 minus 150,000 = 100,000 riyals, plus any loss the owner can prove.
- Completion at the contractor's cost: the owner would have paid another 150,000 riyals under the original contract, but finishing now costs 300,000, so the extra cost is 150,000 riyals, plus proven delay loss.
The figures are only an illustration. The court decides on the evidence in front of it, and in this kind of case the technical report is usually the most important document on file.
What if you are the contractor?
The same rules protect you. Article 107 applies to both sides, so if the owner misses a stage payment, blocks access to the site or changes the scope without agreement, put it in writing at the time. A contractor who simply stops, without explaining why in writing, will struggle later to prove the stoppage was the owner's fault. Keep the payment schedule, your invoices and proof that you asked for each payment when it fell due. Article 171 also helps you: delay caused by something outside your control does not make you liable to compensate.
Expats and foreign businesses: what changes?
- You can file with an iqama. The Najiz claim service accepts a valid iqama as ID, along with a national address.
- Get the contractor's details at the start. You need the defendant's ID number to file. For a company, keep its commercial registration details; for an individual, a copy of the ID, which many owners forget to ask for.
- Acting from abroad. If you are outside Saudi Arabia or relocating, a lawyer holding a valid power of attorney that includes the power to plead can file and follow the case for you.
- Bilingual contracts. If your contract exists in English and Arabic, check which version the contract says prevails, and make sure the scope and dates match in both.
- Do not leave before the record is made. If you are about to leave the Kingdom, have the site inspected and documented first; it is very hard to rebuild that record later.
- After judgment. A judgment that the contractor does not pay is enforced through the enforcement court. Our guide to a travel ban for debt in Saudi Arabia explains what follows when a debtor does not pay.
Common mistakes owners make
- Hiring a new contractor the next day without permission and without recording the site, so the first contractor's work can no longer be measured.
- Relying on a verbal deal with no message that sets out the price, scope and timeline.
- Paying ahead of progress with no link between payments and stages.
- Asking for termination over minor defects, when Article 107 allows the court to refuse it.
- Skipping the formal notice, which is normally a condition for compensation.
- Claiming inflated sums with no engineer's report behind them, which undermines the whole claim.
When do you need a lawyer?
You need a lawyer when the contract value is significant, when the contract is unclear or exists only in messages, when you want to bring in another contractor before judgment, or when the contractor answers with his own claims about late payments or variations. Drafting the notice, choosing the claim and organising the technical evidence decide how strong the file is. See our contracts service, litigation service and real estate service, book a consultation, or call +966 54 668 5254 or message us on WhatsApp.
Sources: Civil Transactions Law, Articles 107, 111, 164, 167, 171, 175, 176 and 177 (text published in Umm Al-Qura); Ministry of Justice: File statement of claim service.
This article is general information about Saudi law, not legal advice for your situation. Talk to a lawyer before acting on it.